Hilltop Park Slope Stabilization Project

Project Timeline

complete
complete

Slope Stabilization Completed Activities

-The contractor placed large rocks (known as riprap) along the entire concrete drainage channel, on both the north and south sides of the channel. This was a temporary measure to prevent damage during the winter storms. Ultimately, all this temporarily placed riprap will be removed. 

-The permanent riprap energy dissipator completed at the western (downstream) end of the project, by the western pedestrian bridge, along with a four-foot tall chain link fence to prevent access to the area.

planned
planned

Slope Stabilization Upcoming Activities

Now that the rainy season is officially over, construction work has resumed. 

Work is starting at the western end of the project by the pedestrian bridge. All the project work will not be done at the same time. Work is currently progressing in 100-foot segments from west to east. The following work is taking place:

-Removing portions of the riprap which was placed as a temporary measure

-Finish grading and incorporating soil amendments into the soil

-Installation of the turf reinforcing mat

-Installation of sod

The construction fence will be in place until the work is completed.

Project Location: Hilltop Park 780 Hilltop Drive

Map location of Hilltop Park

What the project involves:

The City is working to reduce erosion, protect waterways, and plant new trees to keep the park healthy and green. Some aging or unhealthy trees will be removed but will be replaced to support long-term safety and sustainability.

  • Installation of turf reinforcement mat protecting the channel from erosion
  • Installation of sod
  • Planting trees
  • Installation of new irrigation
  • Constructing a concrete structure with cobble stones to slow the water and reduce erosion

Walking Paths and Bridges

Walking path and bridges will remain open in general but occasionally closed for construction activities. Closures are anticipated to last a couple of days at a time. Advance notice of closures will be provided as much as possible.

  • Playground: accessible / no impact
  • Dog Park: accessible / no impact
  • Gazebos: Closed until end of project

We want to hear from you!

Do you have any comments about this project? If so, leave them in the comment box below.

If you have a question about this project please email: HilltopParkCIP@chulavistaca.gov

Thank you for your patience as we improve Hilltop Park for the future.

Have questions about this project?

Email us:

 HilltopParkCIP@chulavistaca.gov

Park Improvement Underway!

Hilltop Park Bridge

Hilltop Park Damage

Hilltop Park Repair